It’s 24hrs before the Kent Ridge trail 1st jamboree ride.
the available work force for the morning session is enough to get some of the cengai/bakau ladder build up and transported to problem area. While the rest do some shopping to get some new material in so to make the ride safer.
With a road ride in the morning, I pop by just after lunch. Just in time for trail work/jamboree briefing.
jamboree roles are clarified and discussed, so are the schedule.
With some work still needed to be done, work group is form and various task spread out for completion.
PLeng and Chi to put up trail signages, which Alano being the only one who haven’t venture into the trail, ride just behind them to check on the signage placement, to give us as much first-timer feedback.
Alvin and Liyana from Nparks try to flatten and pound in the granite chips at the main climb, while superwising the labour force to pound and spread the granite chips.
Max, Ling and Ren Hao, ride/walk the trail with patch up tools and danger markers to make sure the trail is safe for the event.
Jaymes, from SportingSpectrum, Nik and me took the task to net up the staircase ride, so to capture any stray cyclist going right into the 2ft drop at the left side of the trail.
upon completion of the task, we took the time to pour some granite chips over troubled area, and to take advantage of 60+ cyclist, who average 2 laps each and 1 lap of walking the trail to stomp down whatever loose pebbles. This long walk took us 2hrs, and we are suprise how dehydrated we are, not mentioning how hungry i grew.
work hours done
approx 40 manhour clocked on various task for the day.